Regina Revitalization Initiative

This project began in 2009 led by the Government of Saskatchewan. The Crown Investments Corporation commissioned several reports that resulted in a collated into a Feasibility Study. The work included an environmental assessment, a transportation and infrastructure study, and an urban design study of the CP rail site. They also conducted stakeholder consultations. The Province withdrew their participation in the project in March of 2011 because the project would not qualify for federal P3 funding. The Province's Feasibility Study was the starting point for the current project and it can be found here: 2010 Saskatchewan Multipurpose Entertainment Facility Feasibility Report

2011-04-19 10:57:34

Announcement

Mayor Fiacco announces the concept of the Regina Revitalization Initiative

2011-05-30 10:57:34

RRI project established

City Council approves the establishment of the RRI project

2011-06-17 10:57:34

Business Unit Established

A business unit within the City Administration is formally established to continue moving the project forward

2011-08-22 10:57:34

Vision and Guiding Principles Approved

Review of project objectives concludes in City Council’s approval of a Vision and Guiding Principles for the project

2011-09-19 10:57:34

P3

P3 Market Sounding process is initiated by the RRI business unit

2011-12-19 10:57:34

P3 Market Sounding

The results of the P3 Market Sounding process are provided and approved by City Council

2012-02-21 10:57:34

advisor procurement

City Council approves initiation of a procurement process for a Technical Advisor, Project Manager, and Fairness Advisor

2012-02-28 10:57:34

Technical advisor

RFP is issued for the City’s Technical Advisor (Engineering & Architectural)

2012-02-28 10:57:34

Project manager

RFP is issued for the City’s Project Manager

2012-03-05 17:22:02

Background

Background Studies are initiated for Serviceability and Transportation requirements

2012-03-15 17:22:02

p3 policy framework

City Council approves the P3 Policy Framework which guides the potential use of a P3 for the Mosaic Stadium Replacement

2012-04-19 17:22:02

Fairness Advisor

RFP is issued for the P3 Fairness Advisor

2012-04-23 17:22:02

Financial advisor

RFP is issued for the City’s Business and Financial Advisor

2012-04-24 17:22:02

Funding proposal

Formal proposal for funding is provided to the Provincial government

2012-04-24 17:22:02

News Release: planning continues

City to continue planning for Regina Revitalization Project

2012-07-14 17:22:02

News Release: Vision

New Stadium Vision Becomes Reality

2012-07-16 17:22:02

Executive Committee

The following was discussed at the Executive Committee Meeting Wednesday, July 18: EX12-32 - Regina Revitalization Initiative - Non-Binding MOU

2012-07-16 17:22:02

Executive Committee

The following was discussed at the Executive Committee Meeting Wednesday, July 18: EX12-32 - Regina Revitalization Initiative - Non-Binding MOU-Appendix

2012-07-16 17:22:02

Executive committee

The following was discussed at the Executive Committee Meeting Wednesday, July 18: EX12-33 - Regina Revitalization Initiative - Communications Plan

2012-07-20 10:30:36

Citizen Survey

2012 Citizen Survey

2012-09-05 23:52:47

Executive committee

EX12-37 Regina Revitalization Initiative (RRI) - Stadium Procurement Model

2012-09-17 23:52:47

Council

CR12-134 Regina Revitalization Initiative (RRI) – Stadium Procurement Model

2012-10-03 23:52:47

Executive committee

EX12-45 Regina Revitalization Initiative Stadium Project Conceptual Design. EX12-44 Regina Revitalization Initiative (RRI) Canadian Pacific Railway (“CP”) Land Purchase

2012-10-04 23:52:47

Public Information Session

Public Information Session at the Cornwall Centre

2012-10-06 23:52:47

Public Information Session

Public Information Session at the Northgate Mall

2012-10-09 23:52:47

Council

CR12-154 Regina Revitalization Initiative (RRI) Canadian Pacific Railway (“CP”) Land Purchase

2012-11-19 23:52:47

Council

CR12-162 - Stadium Funding – Petition for Referendum

2013-01-03 23:52:47

Stadium Concept

Saskatchewan Roughriders Board approval of the stadium concept and RFQ evaluation criteria

2013-01-07 23:52:47

Stadium Concept

Stadium Funding Committee approval of the stadium concept and RFQ evaluation criteria

2013-01-16 23:52:47

Executive Committee

EX13-1 Regina Revitalization Initiative Stadium Project – Concept Design Approval. EX13-2 RRI – Stadium Project Funding and Financing. EX13-3 Regina Revitalization Initiative (RRI) Stadium Project Request for Qualifications. EX13-4 Regina Revitalization Initiative (RRI) – Additional Canadian Pacific (“CP”) Land Purchases

2013-01-30 22:43:24

Stadium Project RFQ

Request for Qualification for Stadium Project released

2013-02-11 23:52:47

Stadium Site Preparation RFP

Request for Proposal for Stadium Site Preparation released

2013-05-03 09:00:39

Three proponents shortlisted for stadium project

The City’s Stadium Project Request For Qualifications (RFQ) Evaluation Team finalized its review of submissions and announced that three proponent teams have been shortlisted to move into the Request For Proposal (RFP) phase of the Stadium Project.

2013-07-08 09:00:39

City Council approves RRI Stadium Project RFP criteria

City Council approved the Request for Proposals (RFP) criteria for the Stadium Project during its meeting on Monday, July 8.

2013-07-16 09:00:39

Stadium Project RFP issued to three shortlisted proponents

The three proponents will develop their proposals to design, build, construct and provide interim financing of the stadium.

2013-08-15 09:00:39

Building demolition at Stadium Project site

The City of Regina began building demolition work on Thursday, August 15 at 9 a.m.

2013-08-26 09:00:39

Stadium land rezoned

Council approves rezoning to accomodate the new stadium at Evraz Place

2013-11-06 09:00:39

External Financing approved

City Council approves the recommendation for the Deputy City Manager & CFO authorize and negotiate external financing, including signing any necessary documents, to a maximum of $100 million to address the provincial loan financing requirements of the RRI Stadium Project.

2014-01-28 10:48:02

City Council approves terms of $100 million loan

Based on current cash flow projections, the City will require external financing to fund the RRI Stadium Project. On November 6th, 2013, City Council approved that the Deputy City Manager of Corporate Services be authorized to negotiate external financing to a maximum of $100 million and that the required Borrowing Bylaw would be provided to Council for approval along with a report summarizing the financial arrangements.

2014-03-14 10:48:02

PCL Construction Named the Preferred Proponent for the Stadium Project

The City of Regina announced that PCL Construction Management Inc. has been chosen as the Preferred Proponent by the Stadium Project RFP evaluation team. The City of Regina and PCL Construction Management Inc. now move to the next phase of the procurement process, which is contract execution and financial close.

2014-04-11 09:00:00

Site Preparation Continues

Today the City of Regina provided an update on the progress of the site preparation work required for the Regina Revitalization Initiative. Work is underway on water, sewer and road systems as part of the Stadium Project at Evraz Place. This work will also support the development and enhancements to the new Taylor Field and surrounding neighbourhood.

2014-04-14 09:00:00

Delegation of Authority

Delegation of authority be made to the Deputy City Manager & COO to negotiate external financing for the $100M loan payable to the Municipal Financing Corporation of Saskatchewan.

2014-05-20 09:00:00

Important announcement regarding Stadium Project

On Thursday, May 22, 2014, the City of Regina, Province of Saskatchewan, Saskatchewan Roughrider Football Club and Evraz Place will be making a historic announcement at the Credit Union EventPlex. An embargoed technical briefing for the media will take place at 8 a.m. in meeting room six at the Queensbury Convention Centre, followed by the announcement at 10 a.m. at the EventPlex. A public open house will follow at 11:30. Media outlets requesting additional arrangements, including live broadcasting and booking additional interviews following the announcement, are asked to contact the City of Regina Communications Branch by 12 p.m. on Wednesday, May 21. The Elphinstone Street entrance to Evraz Place is currently closed for construction; please use the Lewvan Drive or Princess Street entrances.

2014-06-16 09:00:00

Excavation at the stadium site begins

Excavation at the stadium site begins

2014-06-23 09:00:00

IR 14-8 External Financing

The terms and conditions of the $100.4M loan for the Stadium Project.

2014-07-31 09:00:00

The City Of Regina assumes full control of the approximately 17.5 acres of land purchased from Canadian Pacific

The City Of Regina assumes full control of the approximately 17.5 acres of land purchased from Canadian Pacific

2014-09-18 09:00:00

Regina Revitalization Initiative - Stadium Project Construction update

Since the new Mosaic Stadium official ground breaking in June significant activity at the construction site has taken place, including the recent addition of two tower cranes in the NE and SE areas of the site. The cranes are 215 feet and 200 feet high respectively. Two additional cranes are scheduled for arrival next month and will be used on the construction site until October 2015.

2014-10-29 09:00:00

Four Tower Cranes Operating At Stadium Site

Regina’s skyline has had a significant change in October with the addition of the third and fourth tower cranes at the Regina Revitalization Initiative – Stadium Project construction site. The stadium project is the first PCL commercial project in Regina to have four tower cranes operating at one time.

2015-01-26 09:00:00

Land Disposition & Development

Approval of the Public Investment Development Approach

2015-05-22 09:00:00

New Mosaic Stadium - The First Year

Approximate construction completion is now at 41%

Regina Revitalization Initiative

Launch
Copy this timeline Login to copy this timeline 3d Game mode

Contact us

We'd love to hear from you. Please send questions or feedback to the below email addresses.

Before contacting us, you may wish to visit our FAQs page which has lots of useful info on Tiki-Toki.

We can be contacted by email at: hello@tiki-toki.com.

You can also follow us on twitter at twitter.com/tiki_toki.

If you are having any problems with Tiki-Toki, please contact us as at: help@tiki-toki.com

Close

Edit this timeline

Enter your name and the secret word given to you by the timeline's owner.

3-40 true Name must be at least three characters
3-40 true You need a secret word to edit this timeline

Checking details

Please check details and try again

Go
Close